Skip to main content
N81-scheme-resized-Copy

Dodder Greenway Phases 4 - 6

Dodder Greenway Phases 4 - 6

Phase 4 Dodder Greenway cycle route from Springfield Avenue to Lower Dodder Road.

Phase-7

Project Status - Traffic management to Springfield section is in place with works well under way. Phase 1 which includes crossing to Fairways/ Springfield Ave to be completed this month.

Phase 5 Dodder Greenway Firhouse Road/Butterfield Road 

Phase-6

Project Status: Commencement of works is anticipated for Q3 2023.

Dodder Greenway Firhouse Road/Butterfield Road Part 8 Consultation commenced 06/07/2022 and ended 31/08/2022.

You can still view the details of the Part 8 Consultation here. The works will consist of the following, which will expand the fantastic Dodder Greenway Route further:

  • Construction of a combination of single way and two-way cycle tracks adjacent to the vehicle carriageway
  • Junction amendments to provide safer movement of pedestrians and cyclists
  • Associated services
  • Minor landscaping works
Phase 6 Dodder Greenway On road section from Kiltipper Road to Old Bawn Road.

Phase-6

Project Status- Designs and options for route been considered approx 8 months to completion.